"Unfortunately, the reality of the operating crisis kicked in and the project has been a bit frozen in time," Fremont Public Works Director Hans Larsen told The Mercury News in February about the BART station planned for Washington Boulevard and Osgood Road. Since then, Bay Area voters have approved a regional transit tax and the state has announced its latest round of rail grants. BART has said its share of the tax will keep current service running, and the state grant round included no award for Irvington.
That matters to anyone pricing a home in the Irvington district. Fremont's own history shows when a BART station adds value to nearby homes: once the project is funded, announced and on its way to opening. A station still waiting for full construction funding is a hope. For a buyer near the site this winter, the station is a possible future benefit and should not be part of the price. The way the Fremont market moved this fall gives buyers more room to price that way than they had in the spring.
Where the station stands this November
The Irvington station has been in BART's plans for decades. The Mercury News reported that it was first studied as part of the Warm Springs extension in 1979 and approved by the BART board in 1992. The design is well along, and so is land acquisition. Most of the money to build it is still missing.
The City of Fremont's November 2025 project fact sheet breaks down the funding this way.
| Funding piece | Amount |
|---|---|
| Total project estimate | $289.5 million |
| Alameda CTC Measure BB, approved by county voters in 2014 | $120 million |
| MTC Regional Measure 2 | $2 million |
| Still to be determined | $167.5 million |
The same fact sheet says Fremont had already put in $45 million, the design was about 80% complete, and 14 of the 17 needed properties had been acquired. Its schedule lists construction and opening as "TBD." In a January 28, 2026 letter to State Sen. Aisha Wahab, BART said Fremont was responsible for leading the effort to secure construction funding and that BART could not commit its own funding because of an operating shortfall of about $350 million a year.
The city's project webpage still mentions a possible mid-2026 construction start and a late-2031 opening, but both were conditional on funding. According to The Mercury News, a new timeline cannot be set until funding is found. So a 2031 opening is an old projection, not a date a buyer should plan around.
Why Measure RTM and this month's state grants leave it where it was
Measure RTM passed with 63% of the vote across five counties as of November 12, according to The Oaklandside. In Alameda County, the unofficial count as of November 13 was 67.13% in favor. Counties were expected to certify results by December 3. The tax change takes effect April 1, 2027, and agencies are expected to start receiving funds in July 2027.
Measure RTM protects the BART service Fremont already has. Before the vote, the BART board approved a contingency plan for the case where the measure failed. Its first phase, proposed for January 2027, would have closed 10 stations, including Warm Springs/South Fremont. CBS News Bay Area reported that the plan also included service ending at 9 p.m. and a fare increase of at least 30%. With the measure approved, those cuts were averted. For homeowners near the Fremont and Warm Springs stations, that is the real news from the election.
BART expects about $310 million a year from Measure RTM. Its communications manager, Alicia Trost, told The Oaklandside that the money will mainly pay for current service. "The [RTM] money will not pay for service expansion," she said, adding that any state or federal grants BART receives would go to capital projects.
The state's Transit and Intercity Rail Capital Program, known as TIRCP, is the capital source Fremont officials had named as the best way to close the gap. Its Cycle 8 applications were due May 18, 2026, and awards were scheduled for November 10. The state's list of applications received shows one BART application, for its Ashby station project. On the Cycle 8 award list, BART's award is $25 million for Ashby Transit-Oriented Development Mobility Enhancements in Berkeley. Neither list includes Irvington, so this year's state round did nothing to close the $167.5 million gap in the city's fact sheet.
When Warm Springs homes gained value
Fremont has already seen a BART station change nearby home values once. In 2019, Dr. Shishir Mathur of the Mineta Transportation Institute at San José State University used Alameda and Santa Clara County assessor records to compare values before and after the Warm Springs project was announced. He found that being close to the Warm Springs station was associated with a 9% to 15% increase in single-family home prices. The same study found that owners' gains were large enough to have paid for the whole $802 million extension.
That increase was tied to a project that had funding, was announced and was being built toward an opening. Buyers paid for being near a station once they could count on the station.
Even a funded BART project took longer to finish than planned. The Warm Springs station opened in 2017, but its $41 million west-side pedestrian bridge, first targeted for fall 2018, was still waiting to open in September 2021, according to The Mercury News. The paper reported it opened in February 2022. The city expects the 850-acre Warm Springs Innovation District around the station to eventually add 4,000 homes.
Irvington has not reached the point where Warm Springs values started to rise. A seller who points to the future station as a reason for a higher price is asking a buyer to pay for a step that has not happened yet.
What this fall's Fremont numbers give a buyer
The Fremont market this fall makes it easier to price a home on what is already built. The Bay East Association of REALTORS October 2026 report for Fremont detached homes covers the whole city, not Irvington alone. Here is what it shows.
| Fremont detached homes | March 2026 | October 2025 | October 2026 |
|---|---|---|---|
| Active listings at month end | 92 | 81 | 108 |
| Homes sold during the month | 73 | 79 | 60 |
| Median sale price | $1,750,000 | $1,725,000 | $1,700,000 |
| Average days on market | 12 | 22 | 24 |
| Average sale price as share of list | 106% | 103% | 101% |
The median price barely changed. In October 2026 it was down 1.45% from October 2025. How buyers competed changed more. In March, Fremont buyers paid an average of 6% over the list price, and a home typically sold in under two weeks. In October, buyers paid an average of 1% over list, homes stayed on the market for more than three weeks, and there were 27 more homes for sale at month end than a year earlier. On a $1.7 million home, five percentage points of overbid is about $85,000. A buyer near Osgood Road this winter has more time to question a price and less pressure to pay extra for a station that has no construction schedule.
Across Alameda County, the California Association of REALTORS reported a September 2026 median of $1,265,000 for existing single-family homes, up 1.2% from September 2025. The county median is lower than Fremont's, but it rose slightly year over year while Fremont's dipped. That fits a fall market where prices are holding and buyers are less willing to stretch.
What is already at Osgood and Washington
Some of the station plan is already built, and buyers can count it at full value. The city built a protected intersection at Osgood Road and Washington Boulevard in 2022. The Sabercat Trail already runs nearby, and the station design uses it for access from the east. The design also places a BART parking lot beside the Irvington Town Center business district, extends the East Bay Greenway through the station site, and includes work to stabilize the Gallegos Winery ruins next to the site. Those last pieces depend on the same construction money.
New housing is also planned near the site. The city's upcoming affordable housing list includes Arbor View at 41868 Osgood Road, with 66 rental homes from CRP Affordable Housing and Community Development and leasing expected in spring 2028. It also lists Affordable Housing on Osgood at 41965 and 42021 Osgood Road, with 230 rental homes from MidPen Housing and leasing expected in fall 2028. The Mercury News described both projects as still pending in February. If they are built, they will bring several hundred new households to the blocks around the station site, with or without trains.
For a buyer, the practical step is to compare an Irvington home with recent sales on similar streets elsewhere in Fremont, then count the trail access, the intersection work and the town center as the location advantages they already are. If the station gets construction funding, homes nearby could follow the Warm Springs pattern. In that case the gain goes to the owner, and the buyer has not paid for it at purchase. Our Fremont neighborhood page and buyer's guide cover the rest of the process.
If you own a home near Osgood and Washington and want to know what it is worth based on what is built and selling today, VKG Real Estate Group can prepare a free home valuation using current Fremont sales and the latest status of the Irvington station.